Microsoft Data Center 2 is a mapped data center in Prince William County, VA, operated by Microsoft Data Center LLC and ultimately owned by Microsoft Corporation. DataCentersExposed has documented a 247,070 sq ft footprint at this site.

Reporting by · Updated Jun 14, 2026

Real parent
Microsoft Corporation
Operator
Microsoft Data Center LLC
Est. capacity
~45-100 MW
Footprint
247,070 sq ft
Interconnection
~75 MW
Utility
Virginia Electric & Power Co
Grid
PJM
Attribution & capacity confidence:mediumprimary source

Overview

source: link

Microsoft Data Center 2 is a mapped data center in Prince William County, Virginia, filed by Microsoft Data Center LLC and owned through its parent, Microsoft Corporation. Records put its footprint at 247,070 square feet. The site draws power from Virginia Electric & Power Co inside the PJM grid.

Operator chain

Grid & water — why here

source: HIFLD · EPA
Nearest substation
1.1 mi
Tap139225 · 230 kV
Transmission line
561 ft
115 kV line
Municipal water
No service area
self-supplied or unmapped

The closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.

In the news

source: GDELT

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Statewide cost of this incentive

Virginia reported $1B in Data Center Retail Sales and Use Tax Exemption (Va. Code § 58.1-609.3(18)) for FY2024 (Virginia Joint Legislative Audit and Review Commission (JLARC) / Weldon Cooper Center). Program-wide, not attributable to this site.

source · All Virginia subsidies →

Water use

Modeled estimate~1.4M gpd
Direct (onsite cooling)
~684.7K gpd
Indirect (its electricity)
~720K gpd

No measured record exists, so this is a low-confidence model from 75 MW (interconnection capacity): 1.8 L/kWh cooling (temperate climate) + 0.5 gal/kWh embedded in PJM grid mix. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

What this site costs the grid

source: PJM RPM auction reports
Dominion (Virginia / NC) · 2027/28 auction
$333 /MW-day
Peaked at $444/MW-day in 2025/26 1.65× the rest of PJM

PJM's capacity auction sets a $/MW-day price that utilities pass on to every household and business in the zone. This site sits in PJM's DOM pricing zone, where soaring data-center demand is a documented driver. See the full zone-by-zone breakdown →

This site's capacity-market cost (estimated)
$5.5M to $12.2M/yr

An estimated ~45 to 100 MW of load at the zone's $333/MW-day, annualized — the capacity charge a load this size carries at the current auction price. Estimated from the building footprint at 200 to 400 W/ft² (the typical range for modern data centers). A rough order-of-magnitude figure, not a metered or permitted capacity.

Separately, a typical home in this zone pays an estimated $4 to $10/mo more on the capacity portion of its bill that PJM's market monitor attributes to data-center demand. See your address's full impact →

Air quality near this site

source: AirNow
52
PM2.5
Moderate
36
O3
Good
15
PM10
Good

Air Quality Index from the nearest AirNow reporting area (Northern Virginia), as of 2026-06-10. Regional context — not this facility's own emissions.

Who lives nearby

source: Census ACS 2023
Median household income
$111.4K
People of color
30%
Below poverty
3%
Tract population
4,897

Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.

Nearest school

source: HIFLD / NCES

The nearest public school, Gainesville High in Gainesville, is 1.2 mi from this site (2,038 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.

See something wrong or missing on this page? Suggest a correction.