Amazon AWS Data Center is a mapped data center in St. Joseph County, IN, operated by Amazon Data Services, Inc. and ultimately owned by Amazon.com, Inc..

Reporting by · Updated Jun 14, 2026

Real parent
Amazon.com, Inc.
Operator
Amazon Data Services, Inc.
Utility
Indiana Michigan Power Co
Grid
PJM
Attribution & capacity confidence:mediumprimary source
Status · click to filter

Most sites are mapped — located but awaiting a second source. How we verify

Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.

Overview

source: link

data center

Operator chain

Tax breaks & subsidies

source: Good Jobs First / GASB 77

These tax breaks are recorded to Amazon.com, Inc. (the operator/parent) and may cover this or other sites — no state names the recipient at the facility level.

Total to this operator: $16.7M
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2026 · term yr · source
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2026 · term yr · source
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2026 · term yr · source
  • Long-Term Rural Enterprise Zone (Morrow County School District 1)$16,668,806
    Morrow County School District 1, OR · granted 2024 · term yr · source
  • Texas Qualifying Data Center Exemption$0
    State of Texas · granted 2024 · term yr · source
  • Texas Qualifying Data Center Exemption$0
    State of Texas · granted 2021 · term yr · source
  • Texas Qualifying Data Center Exemption$0
    State of Texas · granted 2021 · term yr · source
  • Texas Qualifying Data Center Exemption$0
    State of Texas · granted 2021 · term yr · source

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

What this site costs the grid

source: PJM RPM auction reports
AEP (Ohio / WV / VA) · 2027/28 auction
$333 /MW-day

PJM's capacity auction sets a $/MW-day price that utilities pass on to every household and business in the zone. This site cleared at the PJM-wide (RTO) price, where soaring data-center demand is a documented driver. See the full zone-by-zone breakdown →

Separately, a typical home in this zone pays an estimated $4 to $10/mo more on the capacity portion of its bill that PJM's market monitor attributes to data-center demand. See your address's full impact →

Air quality near this site

source: AirNow
45
PM2.5
Good
36
O3
Good

Air Quality Index from the nearest AirNow reporting area (South Bend), as of 2026-06-10. Regional context — not this facility's own emissions.

Who lives nearby

source: Census ACS 2023
Median household income
$69.1K
People of color
9%
Below poverty
5%
Tract population
4,325

Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.

Nearest school

source: HIFLD / NCES

The nearest public school, Olive Township Elementary School in New Carlisle, is 3.1 mi from this site (477 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.