Ratcliffe Data Centre
United Kingdom
Source: Primary source
Ratcliffe Data Centre is a proposed data center in United Kingdom. It runs on United Kingdom's grid, which was 36% fossil-fuelled at 217 gCO₂e/kWh in 2025 (Ember).
Reporting by Eric Keller · Updated Jun 12, 2026
Take action
A public decision is in play. This is exactly the moment that changes outcomes — show up and speak.
Your action kit
Sourced arguments and ready-to-send letters — every figure links to a primary record. Edit to add your own story.
Demand a full, public review — not a rubber stamp.
Ask for an independent noise study, a water-and-power impact assessment, enforceable conditions (setbacks, hours, cooling type), and that the record stays open for written comment. Procedural shortcuts have voided approvals elsewhere.
Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.
Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.
Join the campaign
Add your name and we'll email you before every hearing, with what to say and where to show up.
Neighbors taking a stand
Overview
source: linkProposed transmission demand connection on NESO's Existing Agreements (Gate 2) register: 720 MW at Derbyshire Connection Node F 132KV, indicative connection date 2037. A connection agreement is not planning permission — it shows who has reserved grid capacity for a data center.
The grid behind this site
source: Ember · EurostatNational grid context, not this facility's own metering. Full country picture: United Kingdom data centers.
In the news
source: Google News (local + English)- Britain’s Becoming More Efficient and It’s Little to Do With AIBloomberg.com· Aug 26, 2026
- Is a massive data center hub heating up a town outside London?CBS News· Aug 24, 2026
- SNP crackdown on data centre boom amid fears over energy useThe Times· Aug 17, 2026
- Uniper targets data centres in strategy shift, plans €5 bln in investmentReuters· Jul 16, 2026
- Battery storage site in Torridge refused amid fears the countryside is being ‘swallowed up’North Devon Gazette· Jul 3, 2026
- Huge AI data centres in Scotland 'could lead to new homes freeze'Daily Record· Jun 28, 2026