Skip to content
DataCentersExposed
Mapped (unverified)hyperscale

Microsoft data center, Bexar County, TX

Bexar County, TX

Source: OpenStreetMap

Microsoft data center in Bexar County, TX is a mapped facility, operated by Microsoft Corporation. DataCentersExposed has documented a 228,885 sq ft footprint at this site.

Reporting by · Updated Jun 14, 2026

Real parent
Microsoft Corporation
Operator
Microsoft Corporation
Est. capacity
~45-95 MW
Footprint
228,885 sq ft
Utility
Bandera Electric Coop, INC
Grid
ERCO
Attribution & capacity confidence:mediumprimary source
Status · click to filter

Most sites are mapped — located but awaiting a second source. How we verify

Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.

Overview

source: link

Microsoft data center

Operator chain

The grid behind this site, right now

source: ERCOT · gridstatus
Clean right now
48%
Fossil right now
52%
Grid operator
ERCOT
  • Natural Gas41.1%
  • Solar36.3%
  • Coal11.2%
  • Nuclear7.3%
  • Wind3.9%

Real-time generation mix for the ERCOT grid this site draws from, as of Jun 16, 2026, 4:34 PM. ISO-wide, not this facility's own metering. Source: gridstatus.

Tax breaks & subsidies

source: Good Jobs First / GASB 77

These tax breaks are recorded to Microsoft Corporation (the operator/parent) and may cover this or other sites — no state names the recipient at the facility level.

Dollar value not disclosed for these records.
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2024 · term yr · source
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2023 · term yr · source
  • Qualified Data Center Sales Tax Exemption$0
    State of Wisconsin · granted 2023 · term yr · source
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2022 · term yr · source
  • Texas Qualifying Data Center Exemption$0
    State of Texas · granted 2021 · term yr · source
  • Texas Qualifying Large Data Center Project Exemption$0
    State of Texas · granted 2015 · term yr · source
  • Texas Qualifying Data Center Exemption$0
    State of Texas · granted 2013 · term yr · source
  • Texas Qualifying Data Center Exemption$0
    State of Texas · granted 2013 · term yr · source
Statewide cost of this incentive

Texas reported $16.1M in Property used in certain large data center projects; temporary exemption (Texas Tax Code § 151.3595) for FY2025 (Texas Comptroller of Public Accounts). Program-wide, not attributable to this site.

source · All Texas subsidies →

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Nearest school

source: HIFLD / NCES

The nearest public school, Medina Valley Loma Alta Middle in San Antonio, is 0.9 mi from this site (790 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.