Meta El Paso Data Center
"A billion-watt data center in one of America's driest cities, powered by an 813-engine gas plant in the sunniest corner of Texas."
El Paso, El Paso County, TX
Source: Primary source
Meta El Paso Data Center is a under construction data center in El Paso County, TX, operated by Meta Platforms, Inc.. DataCentersExposed has documented 1,000 MW of reported power capacity and a 1,200,000 sq ft footprint at this site.
Reporting by Eric Keller · Updated Jun 17, 2026
Overview
source: linkMeta's El Paso data center, internally called Project Seafox, is a $10 billion build in northeast El Paso that scales to about 1 gigawatt by 2028. At roughly 1,000 acres and 1.2 million square feet, it is Meta's 29th data center, with construction starting in November 2025.
The contradictions stack up. To power it, El Paso Electric proposes the McCloud plant, 366 megawatts from 813 modular gas engines, in a city that gets more than 300 days of sun a year. Meta pays the full cost during a bridge period of up to five years, after which the plant folds into the utility and costs can shift to all ratepayers. Meta counters that it will add clean energy to the Texas grid and match its use, but the gas plant is what physically runs the site.
Water is the deepest concern. El Paso overpumps its aquifer many times over, and the project is permitted for up to 1.5 million gallons a day of potable water because reclaimed supply was not available. The city granted an 80 percent property-tax abatement for about 25 years, and in June 2026 the council rejected canceling the deal, citing up to $1 billion in legal liability.
Operator chain
- Ultimate parentMeta Platforms, Inc.
- Files asMeta Platforms, Inc.
- This facilityMeta El Paso Data Center
Grid & water — why here
source: HIFLD · EPAThe closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.
In the news
source: GDELTTax breaks & subsidies
source: Good Jobs First / GASB 77- El Paso property tax abatement (80%)Tax break$0City of El Paso, TX · granted 2023 · term 25 yr · source
Texas reported $16.1M in Property used in certain large data center projects; temporary exemption (Texas Tax Code § 151.3595) for FY2025 (Texas Comptroller of Public Accounts). Program-wide, not attributable to this site.
Water use
No measured record exists, so this is a low-confidence model from 1,000 MW (disclosed IT power): 2 L/kWh cooling (hot climate) + 0.45 gal/kWh embedded in US grid average. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
Nearest school
source: HIFLD / NCESThe nearest public school, Triumph Public High Schools-El Paso West in El Paso, is 0.2 mi from this site (79 students). 5 public schools sit within a mile of the site.
Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).
Hearings timeline
No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.