Skip to content
DataCentersExposed
Mapped (unverified)

Meta Clonee 1 Data Center

Meath, Ireland

Source: OpenStreetMap

Meta Clonee 1 Data Center is a mapped data center in Meath, Ireland, operated by Facebook USA, Inc. and ultimately owned by Meta Platforms, Inc.. DataCentersExposed has documented a 309,724 sq ft footprint at this site. It runs on Ireland's grid, which was 52% fossil-fuelled at 256 gCO₂e/kWh in 2025 (Ember).

Reporting by · Updated Jun 14, 2026

Real parent
Meta Platforms, Inc.
Operator
Facebook USA, Inc.
Est. capacity
~60-130 MW
Footprint
309,724 sq ft
Grid carbon
256 gCO₂/kWh
Clean electricity
48%
DC power price
22.51¢/kWh
Region
Meath
Attribution & capacity confidence:mediumprimary source
Status · click to filter

Most sites are mapped — located but awaiting a second source. How we verify

Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.

Overview

source: link

Meta data center in Ireland

Operator chain

The grid behind this site

source: Ember · Eurostat
Grid carbon intensity
256 gCO₂/kWh
Clean electricity
48%
Fossil electricity
52%
Data-center power price
22.51¢/kWh

A large data center in Ireland pays 22.51¢/kWh for electricity — a household pays 30.46¢, 26% more than the data center (Eurostat).

Data centres used 21% of Ireland's national electricity in 2023 (CSO Ireland).

National grid context, not this facility's own metering. Full country picture: Ireland data centers.

Methodology & sources

Every row carries a confidence level (high / medium / low) and a source URL. Spot an error? Tell us.