H5 Data Centers Nashville is a mapped data center in TN, operated by H5 Data Centers. DataCentersExposed has documented a 19,700 sq ft footprint at this site.

Reporting by · Updated Jun 18, 2026

Real parent
H5 Data Centers
Operator
H5 Data Centers
Est. capacity
~5-10 MW
Footprint
19,700 sq ft
Attribution & capacity confidence:mediumprimary source

Overview

source: link

H5 Data Centers — colocation facility (22 networks present). Source: PeeringDB.

Operator chain

Grid & water — why here

source: HIFLD · EPA
Nearest substation
0.4 mi
Central
Transmission line
0.2 mi
line
Municipal water
Served
Metro Water Services

The closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.

In the news

source: GDELT

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Nearest school

source: HIFLD / NCES

The nearest public school, Hume - Fogg High in Nashville, is 0.3 mi from this site (898 students). 2 public schools sit within a mile of the site.

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).