Under constructionhyperscale

Google Stillwater Data Center Campus

Perkins Road & Richmond Road · Stillwater, Payne County, OK

Source: Primary source

Google Stillwater Data Center Campus is a under construction data center in Payne County, OK, operated by Google LLC and ultimately owned by Alphabet Inc..

Reporting by · Updated Jun 17, 2026

Real parent
Alphabet Inc.
Operator
Google LLC
Utility
Oklahoma Gas & Electric (OG&E)
Grid
SWPP
Attribution & capacity confidence:mediumprimary source

Overview

source: link

Google's flagship Oklahoma AI and cloud campus, on roughly 400 acres at Perkins Road (US-177) and Richmond Road in Stillwater — a multi-phase, multi-decade buildout planned at up to about $3 billion, with up to six buildings of roughly 300,000 sq ft each. It anchors the $9 billion Oklahoma investment Google announced in August 2025 (alongside the Pryor expansion and new Muskogee County facilities). The Stillwater Planning Commission approved the 202-acre final plat 4-0 on November 4, 2025, and building permits for the first lots were issued; phase one is expected to be operational by 2027. Under the incentive deal Google pays no initial property tax and instead makes payments in lieu of taxes (PILOT) — phase one brings about $900,000 split among Stillwater public schools, Meridian Technology Center, Payne County, and the county health department. Because Stillwater Electric is a public-power provider, OG&E needed voter approval to serve the campus: a franchise vote passed November 5, 2024, with the city set to receive roughly $2.25 million per data center per year once fully operational. At the time of that vote the customer was disclosed only as a "Fortune 100 company," not named as Google.

Operator chain

Known aliases: Richmond Road and Highway 177 Addition · Google Stillwater

The grid behind this site, right now

source: SPP · gridstatus
Clean right now
33%
Fossil right now
67%
Grid operator
SPP
  • Coal34.8%
  • Natural Gas32.1%
  • Wind25.3%
  • Nuclear5.1%
  • Hydro2.7%

Real-time generation mix for the SPP grid this site draws from, as of Aug 17, 2026, 9:30 AM. ISO-wide, not this facility's own metering. Source: gridstatus.

Grid & water — why here

source: HIFLD · EPA
Nearest substation
0.7 mi
Unknown119408 · 69 kV
Transmission line
137 ft
138 kV line
Municipal water
Served
Stillwater Water Plant

The closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.

In the news

source: GDELT

Data-center discussions in Payne County

source: LocalView (CC0)

Local-government meetings in this county that discussed data centers, each cued to the moment. From the public LocalView corpus of government meetings on YouTube — a county-level signal, not necessarily about this specific site.

Stillwater City Council
Nov 4, 2019 · 4 data-center mentions
Stillwater City Council
Nov 15, 2021 · 1 data-center mention
Stillwater City Council
Apr 19, 2021 · 1 data-center mention

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Nearest school

source: HIFLD / NCES

The nearest public school, Richmond Es in Stillwater, is 0.5 mi from this site (344 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.