Skip to content
DataCentersExposed
ProposedcryptoAI / GPU compute

DigiHost North Tonawanda AI Data Center

"A gas peaker that ran a few weeks a year now burns around the clock to mint Bitcoin, lifting its emissions up to 3,500%."

North Tonawanda, Niagara County, NY

Source: Primary source

DigiHost North Tonawanda AI Data Center is a proposed data center in Niagara County, NY, operated by Digi Power X. DataCentersExposed has documented 123 MW of reported power capacity and a 80,000 sq ft footprint at this site.

Reporting by · Updated Jun 17, 2026

Real parent
Operator
Digi Power X
Power
123 MW
Footprint
80,000 sq ft
Utility
National Grid
Grid
NYIS
Attribution & capacity confidence:highprimary source

Overview

source: link

The Fortistar North Tonawanda plant is a 55-megawatt natural-gas peaker in Niagara County, New York, that historically fired only 10 to 74 days a year. Canadian crypto miner Digihost (now Digi Power X, Nasdaq: DGXX) began mining Bitcoin there in 2022, running the plant nearly around the clock behind the meter.

That turned a rarely used peaker into a heavy emitter: about 140,684 tons of carbon dioxide in 2024. The Clean Air Coalition, Sierra Club and Earthjustice sued, and in November 2024 a court vacated the state's approval of the sale for skipping the climate review New York law requires. The city passed a two-year crypto-mining moratorium in July 2024 over a constant cooling-fan drone audible up to a mile away, and residents filed a noise class action in April 2026.

In June 2026 the company pitched converting the mining pods into an 80,000-square-foot enclosed AI and high-performance computing data center. The state air permit remains pending, and the conversion sits before city planners. It is a sharp test of whether the crypto-to-AI pivot cleans up a site or simply relabels it.

Operator chain

  • Files as
    Digi Power X
  • This facility
    DigiHost North Tonawanda AI Data Center

The grid behind this site, right now

source: NYISO · gridstatus
Clean right now
35%
Fossil right now
62%
Grid operator
NYISO
  • Natural Gas61.6%
  • Hydro17.7%
  • Nuclear15.8%
  • Other3.0%
  • Wind1.9%

Real-time generation mix for the NYISO grid this site draws from, as of Aug 17, 2026, 7:55 PM. ISO-wide, not this facility's own metering. Source: gridstatus.

Grid & water — why here

source: HIFLD · EPA
Nearest substation
0.3 mi
Unknown125292 · 115 kV
Transmission line
567 ft
115 kV line
Municipal water
Served
North Tonawanda City

The closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.

In the news

source: GDELT

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Water use

Modeled estimate~1.8M gpd
Direct (onsite cooling)
~748.6K gpd
Indirect (its electricity)
~1.1M gpd

No measured record exists, so this is a low-confidence model from 123 MW (disclosed IT power): 1.2 L/kWh cooling (cool climate) + 0.45 gal/kWh embedded in US grid average. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Nearest school

source: HIFLD / NCES

The nearest public school, Spruce School in North Tonawanda, is 0.8 mi from this site (313 students). 3 public schools sit within a mile of the site.

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.

See something wrong or missing on this page? Suggest a correction.