Childress Data Center

Childress, Childress County, TX

Source: Primary source

Childress Data Center is an operating data center in Childress County, TX, operated by IREN Limited. DataCentersExposed has documented 750 MW of reported power capacity at this site.

Reporting by · Updated Jun 18, 2026

Real parent
Operator
IREN Limited
Power
750 MW
Attribution & capacity confidence:mediumprimary source

Overview

source: link

"Renewable" energy. Bitcoin and AI Imported from the FracTracker Alliance U.S. Data Centers Tracker after review. Details to be corroborated from primary sources.

Operator chain

Grid & water — why here

source: HIFLD · EPA
Nearest substation
1.8 mi
Tesla · 345 kV
Transmission line
399 ft
345 kV line
Municipal water
Served
Rra Kirkland Lazare Ws

The closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Statewide cost of this incentive

Texas reported $16.1M in Property used in certain large data center projects; temporary exemption (Texas Tax Code § 151.3595) for FY2025 (Texas Comptroller of Public Accounts). Program-wide, not attributable to this site.

source · All Texas subsidies →

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Nearest school

source: HIFLD / NCES

The nearest public school, Childress El in Childress, is 8.9 mi from this site (451 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.

See something wrong or missing on this page? Suggest a correction.