Mapped (unverified)colocation
Aruba IT3 - Milan PSP
Ponte San Pietro, Lombardia, Italy
Source: Primary source
Aruba IT3 - Milan PSP is a mapped data center in Lombardia, Italy, operated by Aruba s.p.a.. It runs on Italy's grid, which was 51% fossil-fuelled at 285 gCO₂e/kWh in 2025 (Ember).
Reporting by Eric Keller · Updated Jun 17, 2026
Real parent
Aruba s.p.a.
Operator
Aruba s.p.a.
Grid carbon
285 gCO₂/kWh
Clean electricity
49%
DC power price
18.69¢/kWh
Region
Lombardia
Status · click to filter
Most sites are mapped — located but awaiting a second source. How we verify
Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.
Overview
source: linkAruba S.p.A — colocation facility (22 networks present). Source: PeeringDB.
Operator chain
- Ultimate parentAruba s.p.a.
- Files asAruba s.p.a.
- This facilityAruba IT3 - Milan PSP
The grid behind this site
source: Ember · EurostatGrid carbon intensity
285 gCO₂/kWh
Clean electricity
49%
Fossil electricity
51%
Data-center power price
18.69¢/kWh
A large data center in Italy pays 18.69¢/kWh for electricity — a household pays 31.11¢, 40% more than the data center (Eurostat).
National grid context, not this facility's own metering. Full country picture: Italy data centers.
In the news
source: Google News (local + English)- Aruba Lavora con noi: posizioni aperte e come candidarsiTi Consiglio· Jun 9, 2026
- Ponte San Pietro, Aruba raddoppia la disponibilità di energia da 30 a 60 megawatt: così verrà convertito il quarto blocco dello stabilimentoCorriere Bergamo· Feb 4, 2026
- Aziende Italiane di Data Center Più Grandi ed ImportantiEconomia Italiacom· Jan 27, 2026
- L’ anima sportiva di Aruba: un sodalizio pluriennale con DucatiAruba· Feb 12, 2025
- I nuovi Data Center Aruba aprono a BergamoZeroUno· Nov 5, 2024
- Festa degli Ingegneri 2024, l’ordine premia 70 giovani neoiscritti da 110 e lode: 40 laureati all'UnibgBergamonews· Oct 16, 2024
See something wrong or missing on this page? Suggest a correction.