Skip to content
DataCentersExposed
Operating

Applied Digital / Ellendale Data Center

Dickey County, ND

Source: OpenStreetMap

Applied Digital / Ellendale Data Center is an operating data center in Dickey County, ND. DataCentersExposed has documented 600 MW of reported power capacity and a 2,706,035 sq ft footprint at this site.

Reporting by · Updated Jun 15, 2026

Real parent
Operator
Power
600 MW
Footprint
2,706,035 sq ft
Attribution & capacity confidence:mediumprimary source
Status · click to filter

Most sites are mapped — located but awaiting a second source. How we verify

Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.

Overview

source: link

600 MW energy use, eventually 1 GW with future expansion

In the news

source: GDELT

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Statewide cost of this incentive

North Dakota reported $19.4M in Qualified Data Center sales/use tax exemption for enterprise IT equipment & computer software (N.D.C.C. § 57-39.2-04.17) for FY2024 (North Dakota Legislative Council / Office of State Tax Commissioner (testimony)). Program-wide, not attributable to this site.

source · All North Dakota subsidies →

Water use

Modeled estimate~8.8M gpd
Direct (onsite cooling)
~3.7M gpd
Indirect (its electricity)
~5.2M gpd

No measured record exists, so this is a low-confidence model from 600 MW (disclosed IT power): 1.2 L/kWh cooling (cool climate) + 0.45 gal/kWh embedded in US grid average. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Air quality near this site

source: AirNow
13
PM10
Good
1
PM2.5
Good

Air Quality Index from the nearest AirNow reporting area (Aberdeen), as of 2026-06-10. Regional context — not this facility's own emissions.

Who lives nearby

source: Census ACS 2023
Median household income
$61.8K
People of color
10%
Below poverty
11%
Tract population
1,339

Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.

Nearest school

source: HIFLD / NCES

The nearest public school, Ellendale High Virtual Academy in Ellendale, is 2.5 mi from this site (6 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.