operator
Crusoe
DataCentersExposed tracks 6 data centers operated by Crusoe across 3 states, of which 4 are proposed or under construction, with 13.7 GW of reported power capacity.
Operator added from the FracTracker Alliance U.S. Data Centers Tracker.
Reporting by Eric Keller
Facilities
6
tracked
States
3
footprint
Pipeline
4
proposed / building
Reported power
13.7 GW
6 facilities
Where Crusoe builds
| Facility | Location | Status | MW |
|---|---|---|---|
| Crusoe/ Blue Energy Data Center | Victoria, TX | Proposed | 1,500 |
| Crusoe Childress Data Center (Meta) | Childress, TX | Proposed | — |
| Crusoe Warrenton Data Center (Meta) | Warrenton, MO | Proposed | — |
| Goodnight Campus | Claude, TX | Under construction | 1,030 |
| Project Jade | Cheyenne, WY | Blocked | 10,000 |
| Stargate Abilene (Lancium Clean Campus) | Abilene, TX | 1,200 |