QTS Manassas 1
Prince William County, VA
Source: Primary source
QTS Manassas 1 is a permitted data center in Prince William County, VA. DataCentersExposed has documented a 1,356,387 sq ft footprint at this site.
Reporting by Eric Keller · Updated Aug 29, 2026
Take action
Prince William, Virginia
It was approved. The fight shifts to enforceable conditions, monitoring, and the next one.
Your action kit
Sourced arguments and ready-to-send letters — every figure links to a primary record. Edit to add your own story.
Demand a full, public review — not a rubber stamp.
Ask for an independent noise study, a water-and-power impact assessment, enforceable conditions (setbacks, hours, cooling type), and that the record stays open for written comment. Procedural shortcuts have voided approvals elsewhere.
Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.
Edit freely before sending — it's a starting point. Add your own story; personal comments carry the most weight.
Join the campaign
Add your name and we'll email you before every hearing, with what to say and where to show up.
Neighbors taking a stand
Overview
source: linkData-center campus in Prince William County, Virginia (status: permitted). Case(s): REZ1980-0030. Source: PWC County Mapper Data Center Campuses layer.
Grid & water — why here
source: HIFLD · EPAThe closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.
In the news
source: Google News- Massive Va. data center project won’t go forward after backer ends legal fightThe Washington Post· Jul 9, 2026
- Developer Drops Plans to Build World's Largest Data Center Campus Outside Nation's CapitalBroadband Breakfast· Jul 6, 2026
- Why One Cancelled Data Center Matters to Every Supply Chain ExecutiveLogistics Viewpoints· Jul 6, 2026
- Blackstone Terminates Huge Virginia Data Centre ProjectSilicon UK· Jul 6, 2026
- QTS drops legal fight over massive Prince William County data center projectThe Business Journals· Jul 6, 2026
- QTS drops data center appeal, kills gigawatt PW Digital Gateway project in VirginiaData Center Dynamics· Jul 3, 2026
Tax breaks & subsidies
source: Good Jobs First / GASB 77No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.
Virginia reported $1B in Data Center Retail Sales and Use Tax Exemption (Va. Code § 58.1-609.3(18)) for FY2024 (Virginia Joint Legislative Audit and Review Commission (JLARC) / Weldon Cooper Center). Program-wide, not attributable to this site.
Water use
- Reported withdrawal538.3K gpd2024 · surface · reported as “MANASSAS PLANT” · source
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
What this site costs the grid
source: PJM RPM auction reportsPJM's capacity auction sets a $/MW-day price that utilities pass on to every household and business in the zone. This site sits in PJM's DOM pricing zone, where soaring data-center demand is a documented driver. See the full zone-by-zone breakdown →
An estimated ~270 to 550 MW of load at the zone's $333/MW-day, annualized — the capacity charge a load this size carries at the current auction price. Estimated from the building footprint at 200 to 400 W/ft² (the typical range for modern data centers). A rough order-of-magnitude figure, not a metered or permitted capacity.
Separately, a typical home in this zone pays an estimated $4 to $10/mo more on the capacity portion of its bill that PJM's market monitor attributes to data-center demand. See your address's full impact →
Nearest school
source: HIFLD / NCESThe nearest public school, Unity Reed High in Manassas, is 0.9 mi from this site (2,316 students).
Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).
Hearings timeline
No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.