Skip to content
DataCentersExposed
Proposed

Project Cornmaze

Janesville, Rock County, WI

Source: Primary source

Project Cornmaze is a proposed data center in Rock County, WI, operated by Cambrin LLC., Meta?.

Reporting by · Updated Jun 18, 2026

Real parent
Operator
Cambrin LLC., Meta?
Attribution & capacity confidence:mediumprimary source

Overview

source: link

The land is currently an active gravel pit operated by Rock Road Companies Inc. Imported from the FracTracker Alliance U.S. Data Centers Tracker after review. Details to be corroborated from primary sources.

Operator chain

Grid & water — why here

source: HIFLD · EPA
Nearest substation
416 ft
Tap136969 · 138 kV
Transmission line
206 ft
138 kV line
Municipal water
No service area
self-supplied or unmapped

The closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.

Tax breaks & subsidies

source: Good Jobs First / GASB 77

No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.

Statewide cost of this incentive

Wisconsin reported $40M in Qualified Data Centers sales/use tax exemption (Wis. Stat. § 77.54(70)) for FY2024 (Wisconsin Department of Revenue). Program-wide, not attributable to this site.

source · All Wisconsin subsidies →

Water use

No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.

EPA permits & violations

source: EPA ECHO

No reported violations as of last sync.

Nearest school

source: HIFLD / NCES

The nearest public school, Rock University High in Janesville, is 1.4 mi from this site (91 students).

Schools are sensitive receptors for the noise, backup-generator exhaust, and traffic a large data center brings. Straight-line distance to the nearest public school (HIFLD/NCES, US public schools only).

Hearings timeline

No public-hearing records linked to this site yet. We surface planning-commission and board-of-supervisors dates when a record names a facility. If you know of a hearing on this site, tell us.

See something wrong or missing on this page? Suggest a correction.