IONIC Digital Cedarvale is a mapped data center in Ward County, TX. DataCentersExposed has documented a 2,238,928 sq ft footprint at this site.
Reporting by Eric Keller · Updated Jun 14, 2026
Most sites are mapped — located but awaiting a second source. How we verify
Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.
Overview
source: linkIONIC Digital Cedarvale is a mapped data center in Ward County, TX, operating under the IONIC Digital banner. The site spans 2,238,928 square feet and draws power from Texas-New Mexico Power Co. Beyond that footprint and utility connection, public details about the project's ultimate corporate owner remain thin.
In the news
source: Google News- Ionic Digital Appoints Andy Stewart as Chief Executive OfficerBusiness Wire· Nov 18, 2025
- Crypto firm Ionic Digital looks to go publicData Center Dynamics· Oct 30, 2025
- Ionic, Nscale Deal Highlights AI Growth as Texas Data Center Boom AcceleratesKSST Radio· Oct 15, 2025
- Nscale Wins $14B Microsoft AI Deal, Secures Texas Site via Lease with Ionic DigitalTheEnergyMag· Oct 15, 2025
- Nscale plans massive Texas AI data center for Microsoft in expanded deal for 200,000 Nvidia chipsSeeking Alpha· Oct 15, 2025
- Ionic Digital Board of Directors Sends Proxy Materials and Issues Letter to Stockholders Ahead of Annual MeetingBusiness Wire· Feb 24, 2025
Tax breaks & subsidies
source: Good Jobs First / GASB 77No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.
Texas reported $16.1M in Property used in certain large data center projects; temporary exemption (Texas Tax Code § 151.3595) for FY2025 (Texas Comptroller of Public Accounts). Program-wide, not attributable to this site.
Water use
No measured record exists, so this is a low-confidence model from 175 MW (interconnection capacity): 2 L/kWh cooling (hot climate) + 0.45 gal/kWh embedded in US grid average. How we estimate. Have a utility document? Send it and we'll replace this with the real figure.
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
Who lives nearby
source: Census ACS 2023Demographics of the census tract this facility sits in (American Community Survey 5-year estimates). Environmental-justice context for who bears the local impacts.
Nearest school
source: HIFLD / NCESThe nearest public school, Haynes El in Pecos, is 6.8 mi from this site (403 students).