Skip to content
DataCentersExposed
Mapped (unverified)

Datum Farnborough Data Centre

Hampshire, United Kingdom

Source: OpenStreetMap

Datum Farnborough Data Centre is a mapped data center in Hampshire, United Kingdom, operated by Datum. DataCentersExposed has documented 1 environmental-permit record at this site. It runs on United Kingdom's grid, which was 36% fossil-fuelled at 217 gCO₂e/kWh in 2025 (Ember).

Reporting by · Updated Jun 14, 2026

Real parent
Datum
Operator
Datum
Grid carbon
217 gCO₂/kWh
Clean electricity
64%
Region
Hampshire
Attribution & capacity confidence:mediumprimary source
Status · click to filter

Most sites are mapped — located but awaiting a second source. How we verify

Dot size = disclosed capacity (MW). Smallest = undisclosed, not small.

Overview

source: link

Datum Farnborough Data Centre is a mapped data center in the United Kingdom, operated by Datum. Available records identify it only as a Datum data center, with no ultimate parent, capacity, or footprint figures disclosed. Further details on ownership and operations are not listed in the available record.

Operator chain

  • Ultimate parent
    Datum
  • Files as
    Datum
  • This facility
    Datum Farnborough Data Centre

The grid behind this site

source: Ember · Eurostat
Grid carbon intensity
217 gCO₂/kWh
Clean electricity
64%
Fossil electricity
36%

National grid context, not this facility's own metering. Full country picture: United Kingdom data centers.

Environmental permits

source: Permit register
  • ARK DATA CENTRES LIMITEDEPR/VP3235DJ
    EPR permit · holder "ARK DATA CENTRES LIMITED" · Hart · Combustion; Any Fuel =>50MW - 1.1 A(1) a) · within ~2 km of the mapped site

Methodology & sources

Every row carries a confidence level (high / medium / low) and a source URL. Spot an error? Tell us.