Avaio Digital Partners is a proposed data center in Appomattox County, VA, operated by Avaio Digital. DataCentersExposed has documented 300 MW of reported power capacity and a 250,000 sq ft footprint at this site.
Reporting by Eric Keller · Updated Jun 18, 2026
Overview
source: linkhttps://avaiodigital.com/#projects Imported from the FracTracker Alliance U.S. Data Centers Tracker after review. Details to be corroborated from primary sources.
Operator chain
- Files asAvaio Digital
- This facilityAvaio Digital Partners
Grid & water — why here
source: HIFLD · EPAThe closest existing grid infrastructure and the municipal water system this location sits in — the same constraints the buildout model screens on (it won't site a campus more than ~2 km from a substation or ~5 km from municipal water). Distances are straight-line to public HIFLD/EPA features, not a metered connection.
In the news
source: Google News- $3B data center planned on 452 acres in Appomattox County sparking community pushbackWSET· Mar 22, 2026
- Appomattox residents concerned about planned data centerWDBJ7· Feb 24, 2026
- Avaio Digital Plans $5B Data Center Development in Farmville, VirginiaREBusinessOnline· Jan 29, 2025
- HIT Park in Prince Edward being sold, would become data centerThe Farmville Herald· Jan 28, 2025
- Avaio plans 300MW data center campus in Appomattox County, VirginiaData Center Dynamics· Dec 11, 2024
- Appomattox County strikes deal for data centerCardinal News· Dec 11, 2024
Tax breaks & subsidies
source: Good Jobs First / GASB 77No per-deal tax break is linked to this site yet. No state discloses the recipient of a data-center abatement at the facility level, so per-site deals are rare in the public record. If you have a development agreement or board resolution for this site, send it to us.
Virginia reported $1B in Data Center Retail Sales and Use Tax Exemption (Va. Code § 58.1-609.3(18)) for FY2024 (Virginia Joint Legislative Audit and Review Commission (JLARC) / Weldon Cooper Center). Program-wide, not attributable to this site.
Water use
No public record of this facility's water use. We check state withdrawal reporting for self-supplied sites; municipally supplied sites only become visible through a public-records request to the local water utility — a per-facility request tool is coming. If you have a utility document for this site, send it to us.
EPA permits & violations
source: EPA ECHONo reported violations as of last sync.
Nearest school
source: HIFLD / NCESThe nearest public school, Appomattox Middle in Appomattox, is 787 ft from this site (539 students). 4 public schools sit within a mile of the site.